We are writing to update you on the progress of works to the Westcliff green space.

Week commencing 6th May Lovell started the reduce dig to ensure this area is level. Week commencing 13th May the new turf commenced and should be complete by Friday 17th May. Please be aware that freshly laid turf needs 2 weeks to establish, to ensure this area develops well we ask that no one walks on or uses this area. Lovell will also erect a barrier around this area and sign post it.

We would also like to inform you that the final resin surface to the paths in this area has now changed date. These works are due to take place on Thursday 23rd and Friday 24th May, please be aware that the resin will need 12 hours to dry. Therefore we do ask that during this time period you use your back entrance to access and egress your property if your front door is on the footpath.

Works still to be completed in this area are the final light connection and removal of the old existing estate lighting. Unfortunately we can’t give you a date on this yet as we need UKPN to make their final connections before we can complete this section of works. We are also waiting on the furniture to be delivered, this will include benches and play equipment. This is expected to be delivered to site in June, however we still don’t have an exact date. Once we have final dates for the rest of the outstanding works we will write another letter informing you.

During the operation of construction, works will be carried out between the hours of 8am to 5pm Monday to Friday and 8am to 1pm on a Saturday. Should you have any queries or concerns, please contact me on 0208 731 3800, alternately write me an email to Alexandra.Robins@lovell.co.uk.

We would like to thank you in advance for your cooperation and on going support.