ONGAR HOUSE – ELECTRICS

We are writing to inform you that UKPN will be turning the electrics off to Ongar House on Tuesday 1st September. Works aim to start at 8.30am and the shutdown should last approximately 8 hours.

The reason for them doing these works is to facilitate the electrical supply upgrade. Once works have been completed the electrics will be switched back on to the block.

Should you have any queries or concerns regarding this letter, please contact me on 0208 731 3800, alternately write me an email to Alexandra.Robins@lovell.co.uk. On the day of works please contact 0208 731 3800 for Michael George, Project Manager or Mark Goodearl, Technical Coordinator – MEP.


We would like to thank you in advance for your cooperation and ongoing support. We acknowledge that there will inevitably be some inconvenience during the delivery of these works, but we will do our utmost to keep this to a minimum.